MULTI-MILLION pound construction projects in Dunfermline have been hit by delays and are likely to increase in price.
Fife Council said there has been 'slippage' on the new £7.5m Abbeyview Hub while major transport improvements, such as the £20m-plus Northern Link Road (NLR), may be held up.
Councillors will be given a progress report on the 25 major capital projects – those that cost more than £5m – at the cabinet committee today (Thursday).
The estimated total is now just over £1 billion and Eileen Rowand, executive director of finance and corporate services, warned: "The level of financial risk associated with inflation, and difficulties in supply chains, continues with the impact on rising prices likely to continue for some time to come.
"At this point in time, there is estimated to be an unfunded overspend of £3.215m on the major capital projects which will require a funding solution which will be reviewed in the upcoming capital plan review."
Last March, the council had to find an extra £1m for the Abbeyview Hub, the "anticipated costs" were higher than the available funding of £6.5m, which is due to open in November.
However, Ms Rowand's report said there was slippage of £2.5 million with tenders for the work, which will replace the Tryst Centre and community centre, still to be received.
And the regeneration project in nearby Touch – £745,000 of work that was to be done this financial year will now go ahead in 2023-24 – has been "paused while it is re-scoped".
She confirmed that problems with the supply of building materials "are resulting in delays to projects which, in turn, could lead to increased slippage and increased costs".
On the transport side, there is slippage of £267,000 on the east end of the NLR, a £20m-plus bypass that will serve the new housing estates in the north of Dunfermline and take traffic away from the city centre.
An external consultant has now been appointed to progress the detailed designs for this stretch of the road, which includes a road bridge over the Fife Circle railway line at Halbeath.
The designs should be in this summer, when a planning application for the bridge is expected. The east end of the NLR is due for completion in 2026-27.
A deal to buy land needed for the bypass, from the owners of Halbeath Retail Park, is progressing.
There is also £296,000 of slippage on the installation of traffic lights on the Bothwell Gardens roundabout in Dunfermline.
Detailed designs should now be finished this summer.
On the plus side, the potential risk of a rise in the bill for the Dunfermline Learning Campus – the schools element will cost £122m – "significantly reduced" following the award of the construction contract in July last year.
Ms Rowand said this "limits the impact of inflation on the project" although some £500,000 of work that was to be done this year will now be carried over into 2023-24.
However, there is concern that more money will be needed to pay for the council's affordable housing programme.
Thousands of new homes are planned and there's an approved budget of £161m for phase three but it's likely to cost more "due to the unit cost per property continuing to rise".
She said a further risk would be the availability of funds for larger projects from developer contributions.
With thousands of new homes to be built, housebuilders have been asked to fund the cost of new primary schools, in areas like Halbeath, Broomhall and Wellwood, as well as contributions towards transport improvements.
However, they are asked, generally, to pay once so many houses have been built and if housebuilding is delayed or hasn't started, the schools and roads may not be built as soon as the council would like.